The challenge
Develop and flight test a novel hydrogen-powered uncrewed aircraft in under 12 months, while achieving the regulatory approvals necessary for safe operation within UK airspace.
The solution
CAeS leveraged its extensive certification, airworthiness, and flight test heritage to lead the UK SORA process for the Stingray ST-5 programme. Working closely with regulators and stakeholders, the team developed the operational safety case, airworthiness strategy, and supporting evidence required to progress efficiently from concept to approved flight operations.
The output
Stingray ST-5 successfully progressed from an early-stage concept to flight testing in under 12 months. The programme demonstrated not only a novel hydrogen-powered, blended-wing-body UAV, but also CAeS's ability to deliver a clear, regulator-ready pathway to flight through the UK SORA framework. CAeS SORA Services: 1) Development of SORA applications and supporting safety cases 2) Operational risk assessment and mitigation strategy definition 3) Regulatory engagement and approval support 4) Flightworthiness, airworthiness and certification expertise for UAS operations 5) Flight test approval and operational readiness planning 6) End-to-end support from concept through to authorised flight operations Enabling innovative UAV operators to move from concept to compliant flight with confidence.